%20(1).avif)
A commercial kitchen renovation is a high-stakes operation. For hotels, resorts, country clubs, and healthcare facilities, kitchen downtime directly impacts revenue, guest satisfaction, and brand reputation. Yet without a clear commercial kitchen renovation timeline, even well-funded projects spiral into costly delays, failed inspections, and operational chaos.
The reality? Most commercial kitchen renovations take 12-20 weeks from permit application to reopening — but that's only when properly sequenced. Permit processing alone averages 3-6 weeks in major markets. Equipment lead times for commercial-grade appliances stretch 10-16 weeks. Multi-agency inspections create bottlenecks that can stall progress for days or weeks.
This guide breaks down the commercial kitchen renovation timeline week by week, showing exactly what happens during each phase — from design finalization to final health department approval. You'll learn which milestones drive the critical path, where delays typically occur, and how to maintain food service operations while construction proceeds on schedule.
Understanding Commercial Kitchen Renovation Timelines
Typical Duration: 8-20 Weeks for Most Projects
Commercial kitchen renovation timelines vary significantly based on project scope. Minor equipment upgrades and cosmetic refreshes complete in 6-8 weeks. Mid-scale renovations involving layout modifications, new equipment installations, and finish upgrades typically require 12-16 weeks. Comprehensive gut renovations with structural modifications and utility relocations extend to 18-24 weeks or longer.
According to the National Restaurant Association, 73% of foodservice operators underestimate their restaurant kitchen renovation duration by at least three weeks. The gap stems from underestimating permit processing, equipment procurement, and inspection cycles — factors largely outside contractor control.
The commercial kitchen construction timeline operates on a critical path determined by sequential dependencies. You cannot install hood systems before structural framing is complete. Health inspections cannot occur before fire suppression systems are tested. Equipment cannot be commissioned before utility connections pass inspection.

Pre-Construction Phase (Weeks 1-4)
Week 1-2: Design Finalization and Engineering Review
The commercial kitchen renovation timeline officially begins when conceptual designs transition to construction-ready documents. During weeks 1-2, architects and foodservice consultants finalize equipment specifications, confirm layout dimensions, and coordinate mechanical, electrical, and plumbing (MEP) systems.
This phase requires extensive input from kitchen management and executive chefs. Traffic flow patterns, station adjacencies, storage volumes, and equipment capacities must align with actual menu requirements and service volumes.
Engineering drawings undergo rigorous review. Structural engineers verify that floor loading can support new equipment. Electrical engineers calculate power requirements, often discovering that service panels need upgrades. According to Foodservice Consultants Society International (FCSI), detailed pre-construction planning reduces overall project duration by 15-20%.
Week 3-4: Permitting and Approval Process
Permit processing represents the least controllable aspect of kitchen renovation planning. Once submitted, applications enter review queues managed by multiple agencies: building departments, fire marshals, and health departments.
Building departments review structural modifications, egress requirements, and accessibility compliance. Fire marshals scrutinize hood systems, fire suppression equipment, and fire-rated construction. NFPA 96 (Standard for Ventilation Control and Fire Protection of Commercial Cooking Operations) governs hood design and suppression systems.
Health departments evaluate layout configurations, equipment specifications, handwashing facilities, and sanitation systems. The FDA Food Code establishes baseline requirements, but local health departments often impose additional standards.
Permit acquisition timing varies dramatically by location. Fast-track jurisdictions complete approvals in 2-3 weeks. Standard processing takes 3-6 weeks. Complex projects in slow-review jurisdictions extend to 8-12 weeks.
Demolition and Site Preparation (Weeks 5-6)
Week 5: Kitchen Shutdown and Demolition
With permits secured, demolition marks the transition from planning to physical construction. Week 5 begins with kitchen shutdown, equipment disconnection, and protection of adjacent spaces. General contractors establish containment barriers using temporary walls and negative air pressure systems to prevent dust migration into dining rooms or guest areas.
Demolition crews systematically remove existing equipment, casework, wall finishes, ceiling tiles, and flooring. A typical 2,000-square-foot commercial kitchen renovation generates 15-25 tons of demolition debris.
During this phase, maintaining alternative food service becomes critical for hotels and healthcare facilities. Mobile Culinaire's mobile kitchen solutions provide fully equipped temporary facilities that keep operations running, with deployment timelines of 2-4 weeks from initial inquiry to installation.
Week 6: Hazardous Material Remediation and Structural Assessment
Week 6 addresses conditions discovered during demolition. Hazardous material findings occur in approximately 35% of commercial kitchen renovations in buildings constructed before 1980, according to Environmental Protection Agency surveys. Asbestos-containing materials commonly appear in floor tiles, ceiling tiles, and pipe insulation.
Discovery of asbestos or lead triggers specific protocols. Certified testing labs analyze samples. If hazardous materials are confirmed, licensed abatement contractors perform removal following EPA regulations. Abatement adds 1-3 weeks to the timeline and increases costs by $15,000-$75,000.
Structural assessment verifies existing conditions against design assumptions. Equipment foundations for heavy appliances require adequate structural support. Utility infrastructure assessment also occurs — plumbers verify water supply pressure, electricians confirm service panel amperage, and HVAC technicians evaluate exhaust fan capacities.

Rough Construction Phase (Weeks 7-10)
Week 7-8: Structural Work and MEP Rough-Ins
Rough construction begins once demolition debris is cleared. Weeks 7-8 focus on infrastructure: structural modifications, mechanical systems, electrical distribution, and plumbing networks.
Modern commercial kitchens consume enormous power — 400-600 amps for mid-sized facilities. Electricians install new service panels, run conduit to equipment locations, and verify grounding systems. Every piece of commercial cooking equipment requires dedicated circuits: 50-60 amps for ranges, 30-40 amps for convection ovens.
Plumbing rough-in includes water supply piping, drainage systems, grease interceptors, and natural gas distribution. Grease interceptors — mandatory in virtually all jurisdictions — install underground or inside using specially designed units.
HVAC rough-in addresses makeup air systems and space conditioning. Makeup air — tempered fresh air that replaces air exhausted through hood systems — prevents negative building pressure. Without adequate makeup air, kitchens experience poor hood capture efficiency and uncomfortable working conditions, as documented by ASHRAE (American Society of Heating, Refrigerating and Air-Conditioning Engineers).
Most jurisdictions require inspections before concealing work: rough electrical, rough plumbing, and structural inspections. Failed inspections halt work until deficiencies are corrected — delays that can add 3-7 days per occurrence.
Week 9-10: Fire Suppression, HVAC, and Hood Installation
Weeks 9-10 bring installation of hood assemblies, fire suppression equipment, and HVAC components. Commercial hoods weighing 500-2,000 pounds require substantial structural support, typically steel channels anchored to building structure.
Type I hoods over cooking equipment that produces grease-laden vapor require specific construction: 16-18 gauge stainless steel, continuous welded seams, and removable baffle filters. Ductwork must meet stringent NFPA 96 requirements: 16-gauge or heavier steel, fully welded seams, and accessible cleanout ports. Improper duct installation represents the leading cause of fire marshal inspection failures.
Fire suppression system installation occurs simultaneously. Wet chemical suppression systems include detection elements, control panels, chemical storage tanks, and discharge nozzles positioned over cooking surfaces. Licensed fire suppression contractors install these systems following NFPA 17A standards.
Exhaust fans — typically roof-mounted — install during weeks 9-10. Variable frequency drives increasingly appear on exhaust fans, modulating fan speed based on cooking loads and reducing energy consumption by 30-50%.
Finish Construction Phase (Weeks 11-14)
Week 11-12: Wall Finishes, Flooring, and Millwork
With rough construction complete, weeks 11-12 transform rough construction into finished spaces ready for equipment installation.
Most commercial kitchens incorporate FRP (fiber-reinforced plastic) panels or stainless steel wall covering for durability and cleanability. FRP installs over moisture-resistant backing and provides decades of low-maintenance service. Stainless steel wall panels provide ultimate durability in high-impact areas.
Flooring represents one of the most scrutinized aspects of commercial kitchen finish work. Health departments mandate smooth, non-absorbent, easily cleanable surfaces. The most common solution remains quarry tile: dense, vitreous clay tiles set in epoxy mortar with epoxy grout.
Most health codes require floor drains with floors sloped 1/4 inch per foot toward drains. Proper slope ensures effective cleaning and prevents standing water that harbors bacteria.
Stainless steel casework — countertops, cabinets, shelving — installs after flooring is complete. Commercial-grade casework uses 14 or 16 gauge material, fully welded and ground smooth.
Week 13-14: Equipment Installation and Integration
Weeks 13-14 transform finished spaces into functional kitchens through equipment installation. Equipment delivery timing proves critical. Delayed equipment shipments represent the second-most common reason for schedule overruns, behind only permit processing.
Installation begins with large equipment: walk-in coolers and freezers, conveyor dishwashers, and custom fabricated cook lines. Cooking equipment follows — ranges, ovens, fryers, griddles, and charbroilers require both utility connections and proper positioning under hood systems.
Equipment spacing follows NFPA 96 requirements: 6-inch minimum clearance from combustible construction and proper positioning relative to hood capture zones. Dishwashing equipment installation requires attention to water supply pressure, drainage flow rates, and booster heaters for 180°F final rinse temperatures mandated by health codes.
Systems integration and commissioning begin during week 14. Equipment startups verify proper operation: refrigeration achieving proper temperatures, cooking equipment reaching specified temperatures, and ventilation systems maintaining proper airflow.

Inspection and Commissioning (Weeks 15-17)
Week 15-16: Multi-Agency Inspections (Fire, Health, Building)
Inspection week represents the most critical period in any commercial kitchen remodel schedule. Multiple agencies conduct independent inspections, each with authority to prevent occupancy until deficiencies are corrected.
Building department final inspections verify that constructed work matches permitted drawings. Fire marshal inspections focus on hood systems, fire suppression equipment, exit paths, and emergency lighting. Fire suppression system testing — witnessed by fire marshal or designee — occurs during inspection week.
Health department inspections typically occur last. Inspectors verify compliance with FDA Food Code provisions: proper handwash sink placement, adequate lighting levels (50 foot-candles minimum), proper floor drainage, and compliant storage configurations.
Common health department findings include missing thermometers on refrigeration equipment, inadequate handwash sink access, improper floor-wall junctures allowing pest harborage, and insufficient ventilation. Each finding must be corrected before re-inspection.
Industry data from the International Code Council indicates approximately 35% of commercial kitchen projects require at least one re-inspection.
Week 16-17: Deficiency Correction and Re-Inspection
Weeks 16-17 address deficiencies and secure final approvals. Minor findings correct in hours. Moderate findings require 1-3 days. Major findings potentially add 1-2 weeks.
Certificate of Occupancy (CO) issuance occurs once all inspections pass. Without CO, health departments cannot issue operating permits required for food service. Operating permit application occurs during weeks 16-17 after verifying CO issuance.
Final Preparation and Opening (Weeks 18-20)
Week 18-19: Staff Training and Operational Testing
With inspections passed, weeks 18-19 focus on operational readiness. Equipment training involves manufacturer representatives providing hands-on instruction. Mock services reveal workflow bottlenecks, equipment access issues, or missing tools requiring correction.
System testing verifies that integrated systems perform as designed under full load conditions. Many operators conduct friends-and-family test services during week 19, producing full menus at operational volumes but serving limited guests.
Week 20: Soft Opening and Full Service Launch
Week 20 brings phased return to full operations. Soft openings — limited menu, reduced capacity — allow kitchen staff to build confidence while identifying remaining issues. Full service launch occurs once soft opening identifies and corrects any remaining issues.
Post-opening support from contractors typically continues through warranty periods. Many operators engage foodservice consultants for post-opening evaluation 30-60 days after launch.
Variables That Impact Your Commercial Kitchen Renovation Timeline
Permitting processes remain the least predictable element. Electronic plan submission systems accelerate processing in progressive jurisdictions by 30-40%. However, many jurisdictions still rely on manual processes extending timelines. Multi-jurisdiction projects create coordination challenges, and special districts add 2-8 weeks to permitting.
Equipment availability dramatically affects schedules. Standard cooking equipment ships within 6-10 weeks. Custom configurations extend to 12-16 weeks. Imported European equipment requires 16-24 weeks from order to delivery. Walk-in coolers and custom-fabricated hood systems fall into the long-lead category at 10-14 weeks.
Unknown conditions discovered during demolition represent the most common cause of mid-project adjustments. Structural discoveries, code compliance issues, and hazardous materials almost always extend schedules by 1-3 weeks. Contingency time and budget address these unknowns — experienced operators budget 10-15% contingency and add 2-3 weeks schedule float.

How Mobile Kitchens Maintain Operations During Renovation
Deployment Timeline: 2-4 Weeks from Inquiry to Installation
Maintaining food service during renovations represents a critical challenge for hospitality operators. Mobile kitchen solutions from Mobile Culinaire provide fully equipped temporary facilities that maintain operations throughout renovation periods.
The mobile kitchen deployment timeline typically spans 2-4 weeks. Week 1 involves needs assessment and site evaluation. Weeks 2-3 focus on unit configuration and utility coordination. Week 3-4 brings delivery, positioning, and connection. Once positioned, technicians connect utilities and commission equipment — typically achieving operational status within 24-48 hours of arrival.
Compared to the 18-20 week permanent kitchen renovation timeline, mobile kitchen deployment proves remarkably efficient, enabling operators to maintain service continuity and protect revenue streams.
Integrating Mobile Kitchen Setup with Your Renovation Schedule
Strategic integration requires coordination and advance planning. Mobile kitchens ideally achieve operational status 1-2 weeks before permanent kitchen closure, allowing workflow adaptation and staff training.
Rental costs typically range $5,000-$50,000 monthly depending on unit size and equipment specification. Hotels and resorts typically calculate break-even at 2-3 weeks of maintained food and beverage revenue versus rental costs. Understanding mobile kitchen rental costs and reviewing successful use cases helps operators evaluate deployment viability.
Conclusion
The commercial kitchen renovation timeline spans 12-20 weeks for most projects — from permit submission through final health department approval. Success requires early kitchen renovation planning, comprehensive design development, strategic equipment procurement, and contingency allowances for unknowns.
Understanding the week-by-week progression — pre-construction permitting, demolition, rough construction, finish work, equipment installation, inspections, and commissioning — enables realistic schedule development and stakeholder communication. Recognizing variables that extend timelines allows contingency planning that protects opening dates and budgets.
For hospitality operations unable to suspend food service during renovations, maintaining operational continuity represents the critical challenge. Mobile kitchen deployment integrates seamlessly with permanent kitchen renovation schedules, protecting revenue streams and guest satisfaction throughout construction periods.
Planning a commercial kitchen renovation for your hotel, resort, or foodservice facility? Mobile Culinaire's fully equipped mobile kitchens keep your operations running seamlessly during construction — deployed in as little as 2-4 weeks. Our turnkey rental service includes delivery, installation, and removal, giving you complete peace of mind while your permanent kitchen undergoes transformation. Contact our team today to discuss your renovation timeline and explore mobile kitchen solutions tailored to your facility. For additional guidance on renovation preparation, review our comprehensive commercial kitchen renovation preparation guide.

People Also Ask (FAQ)
How long does a typical commercial kitchen renovation take?
Most commercial kitchen renovations take 12-20 weeks from permit application to reopening, though timelines vary significantly. Minor equipment refreshes might complete in 6-8 weeks, while full gut renovations can extend to 24 weeks. According to facility management data, 65% of commercial kitchen projects experience at least one delay, typically adding 2-4 weeks due to permit processing, material availability, or inspection failures.
Can a restaurant stay open during a kitchen renovation?
Yes, many restaurants maintain operations through phased construction or mobile kitchen deployment. Phased renovations allow sections to remain operational while others are remodeled, though this typically extends the timeline by 20-30%. Mobile Culinaire's turnkey kitchen trailers can be installed in 2-4 weeks, enabling full-service operations to continue uninterrupted while permanent renovations proceed.
What are the most common causes of commercial kitchen renovation delays?
The three primary delay factors are permit processing (averaging 2-6 weeks depending on jurisdiction), discovery of code violations or structural issues during demolition (adding 1-3 weeks), and equipment lead times for commercial-grade appliances (currently 8-16 weeks for specialized items). Multi-agency inspections also create bottlenecks, with each failed inspection potentially adding 1-2 weeks for corrections and re-inspection scheduling.
Testimonial

"What is standing out when you look at the mobile kitchen operation is the efficiency that we can really achieve because it's built for that."
Tell us about your kitchen needs and request a quote.
.png)
Turnkey mobile kitchen
.png)
Proudly made in-house in the USA
.png)
Commercial grade kitchen equipment
.png)
Code-compliant
Trusted by Industry Leaders




%20(1).avif)
%20(1).avif)